Energy efficiency improvement of the Building, A, B and C of the Hotel Mrągovo Resort & Spa (Q132150): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Changed an Item)
(‎Created claim: summary (P836): The project will carry out investment activities aimed at increasing the energy efficiency of the Building together with parts A, B and C of the Hotel Mrągovo Resort & Spa. The scope of the project will include the following tasks: refurbishment of the window envelope, upgrading of the external door envelope, upgrading of the envelope wall, upgrading of the envelope, modernisation of the roof, modernisation of the heating system, modernisation o...)
Property / summary
 
The project will carry out investment activities aimed at increasing the energy efficiency of the Building together with parts A, B and C of the Hotel Mrągovo Resort & Spa. The scope of the project will include the following tasks: refurbishment of the window envelope, upgrading of the external door envelope, upgrading of the envelope wall, upgrading of the envelope, modernisation of the roof, modernisation of the heating system, modernisation of the heating system. All the works will be carried out by the general contractor selected through the tender procedure (the project will be carried out under the design and demolition formula). The project will run from 1 March 2019 to 31 December 2019 on plot No 245/6. The project coordinator, one of the applicant’s staff, will be responsible for managing the project. This project is in line with the objectives of Priority Axis 4 Energy efficiency for reducing primary energy consumption in buildings. Thanks to the investment efforts for the thermal renovation of buildings and the modernisation of the heating system and the modernisation of the hot water system, the consumption of the main A, B and C buildings will be reduced compared to the current situation. The specific objectives of the project and their compliance with the ROP WiM 2014-2020 are laid down in the next section of this application for funding. (English)
Property / summary: The project will carry out investment activities aimed at increasing the energy efficiency of the Building together with parts A, B and C of the Hotel Mrągovo Resort & Spa. The scope of the project will include the following tasks: refurbishment of the window envelope, upgrading of the external door envelope, upgrading of the envelope wall, upgrading of the envelope, modernisation of the roof, modernisation of the heating system, modernisation of the heating system. All the works will be carried out by the general contractor selected through the tender procedure (the project will be carried out under the design and demolition formula). The project will run from 1 March 2019 to 31 December 2019 on plot No 245/6. The project coordinator, one of the applicant’s staff, will be responsible for managing the project. This project is in line with the objectives of Priority Axis 4 Energy efficiency for reducing primary energy consumption in buildings. Thanks to the investment efforts for the thermal renovation of buildings and the modernisation of the heating system and the modernisation of the hot water system, the consumption of the main A, B and C buildings will be reduced compared to the current situation. The specific objectives of the project and their compliance with the ROP WiM 2014-2020 are laid down in the next section of this application for funding. (English) / rank
 
Normal rank

Revision as of 20:07, 10 March 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
Energy efficiency improvement of the Building, A, B and C of the Hotel Mrągovo Resort & Spa
Project in Poland financed by DG Regio

    Statements

    0 references
    2,220,121.95 zloty
    0 references
    532,829.268 Euro
    13 January 2020
    0 references
    4,964,999.99 zloty
    0 references
    1,191,599.9976000001 Euro
    13 January 2020
    0 references
    55.0 percent
    0 references
    1 March 2019
    0 references
    31 December 2019
    0 references
    DEPORIUM INC. SPÓŁKA Z OGRANICZONĄ ODPOWIEDZIALNOŚCIĄ
    0 references

    53°52'7.0"N, 21°18'18.7"E
    0 references
    W ramach projektu przeprowadzone będą działania inwestycyjne mające na celu zwiększenie efektywności energetycznej Budynku Głównego wraz z częściami A, B i C Hotelu Mrągowo Resort & Spa. Zakres rzeczowy projektu będzie obejmował następujące zadania: modernizacja przegrody okno zewnętrzne, modernizacja przegrody drzwi zewnętrzne, modernizacja przegrody ściana zewnętrzna, modernizacja przegrody dach, modernizacja ciepłej wody użytkowej, modernizacja systemu grzewczego. Wszystkie prace będą prowadzone przez generalnego wykonawcę, wyłonionych w drodze postępowania ofertowego (projekt będzie realizowany w formule zaprojektuj i wybuduj). Projekt będzie realizowany od 1 marca 2019 do 31 grudnia 2019 roku, na działce o numerze 245/6. Nad prawidłową realizacją projektu będzie czuwał koordynator projektu, jeden z pracowników Wnioskodawcy. Niniejszy projekt jest zgodny z założeniami dla osi priorytetowej nr 4 Efektywność energetyczna w zakresie obniżenia zużycia energii pierwotnej w budynkach. Dzięki działaniom inwestycyjnym polegającym na termomodernizacji budynków oraz modernizacji systemu grzewczego i modernizacji systemu ciepłej wody użytkowej zmniejszy się zużycie energii w budynku głównym A, B i C w porównaniu do sytuacji obecnej. Szczegółowe cele projektu oraz ich zgodność z RPO WiM 2014-2020 zostały określone w kolejnym punkcie niniejszego wniosku o dofinansowanie. (Polish)
    0 references
    The project will carry out investment activities aimed at increasing the energy efficiency of the Building together with parts A, B and C of the Hotel Mrągovo Resort & Spa. The scope of the project will include the following tasks: refurbishment of the window envelope, upgrading of the external door envelope, upgrading of the envelope wall, upgrading of the envelope, modernisation of the roof, modernisation of the heating system, modernisation of the heating system. All the works will be carried out by the general contractor selected through the tender procedure (the project will be carried out under the design and demolition formula). The project will run from 1 March 2019 to 31 December 2019 on plot No 245/6. The project coordinator, one of the applicant’s staff, will be responsible for managing the project. This project is in line with the objectives of Priority Axis 4 Energy efficiency for reducing primary energy consumption in buildings. Thanks to the investment efforts for the thermal renovation of buildings and the modernisation of the heating system and the modernisation of the hot water system, the consumption of the main A, B and C buildings will be reduced compared to the current situation. The specific objectives of the project and their compliance with the ROP WiM 2014-2020 are laid down in the next section of this application for funding. (English)
    0 references

    Identifiers

    RPWM.04.02.00-28-0021/17
    0 references