Construction of the bypass of Brasov Municipality, Tronson I (DN1-DN11), II (DN11-DN13) and III (DN 13-DN 1) Phase II (Q3098995): Difference between revisions
Jump to navigation
Jump to search
(Changed an Item: Edited by the materialized bot - inferring region from the coordinates) |
(Changed label, description and/or aliases in fr: translated_label) |
||
label / fr | label / fr | ||
Construction du contournement de la municipalité de Brasov, Tronson I (DN1-DN11), II (DN11-DN13) et III (DN 13-DN 1) Phase II |
Revision as of 14:41, 27 November 2021
Project Q3098995 in Romania
Language | Label | Description | Also known as |
---|---|---|---|
English | Construction of the bypass of Brasov Municipality, Tronson I (DN1-DN11), II (DN11-DN13) and III (DN 13-DN 1) Phase II |
Project Q3098995 in Romania |
Statements
64,611,918.79 Romanian Leu
0 references
12,922,383.758000001 Euro
0.2 Euro
13 September 2021
0 references
76,014,022.11 Romanian Leu
0 references
85.0 percent
0 references
1 January 2014
0 references
30 April 2019
0 references
COMPANIA NAŢIONALĂ DE ADMINISTRARE A INFRASTRUCTURII RUTIERE S.A./Departament Documentatii Obtinere Fonduri Externe
0 references
Obiectivul principal al proiectului „Constructia variantei de ocolire a municipiului Brasov” consta in constructia a 13,63 km de drum nou la profil 2x2, precum si largirea a 4.924 km de la profil 2x2 la profil 4x4. Finalizarea lurarilor va duce la reducerea timpului de parcurs pentru traversarea orasului Brasov cu cca 12 minute. Prezentul proiect este un proiect fazat, Faza I a fost finanțata din POS-T în cadrul Axei Prioritare 2 ”Modernizarea si dezvoltarea infrastructurii nationale de transport in afara axelor prioritare TEN-T in scopul dezvoltării unui sistem național durabil de transport”, domeniul major de intervenție 2.1 ”Modernizarea si dezvoltarea infrastructurii rutiere naționale”, iar Faza a II-a face obiectul prezentei aplicatii pentru finantare POIM, Axa Prioritară 2 - "Dezvoltarea unui sistem de transport multimodal, de calitate, durabil şi eficient" , Obiectivul specific 2.1 "Creşterea mobilităţii pe reţeaua rutieră TEN-T globală". (Romanian)
0 references
The main objective of the project “Construction of Brasov bypass” is to build 13.63 km of new road at 2x2 profile, as well as widening 4.924 km from profile 2x2 to 4x4 profile. The completion of the pickles will reduce the time to cross Brasov by about 12 minutes. This project is a phased project, Phase I was financed from POS-T under Priority Axis 2 “Modernisation and development of national transport infrastructure outside the TEN-T priority axes in order to develop a sustainable national transport system”, major area of intervention 2.1 “Modernisation and development of national road infrastructure”, and Phase II is the subject of this application for financing LIOP, Priority Axis 2 – “Development of a multimodal, quality, sustainable and efficient transport system”, Specific Objective 2.1 “Increasing mobility on the comprehensive TEN-T road network”. (English)
16 September 2021
0 references
Municipiul Braşov, Romania
0 references
Identifiers
111081
0 references