(Created claim: summary (P836): The project involves the construction of a PV power plant with an installed capacity of 0.6 MW and a SN cable line on plots Nos 125, 111, 67 and 117 within the municipality of Cyclists and the execution of a photovoltaic installation with an installed capacity of 0.031 MW covering the company’s own needs on electricity. Piasecka 32 A, Ktowel in the Municipality of Mełgiev. The applicant is entitled to the property on which the project will be im...) |
||
Property / summary | |||
The project involves the construction of a PV power plant with an installed capacity of 0.6 MW and a SN cable line on plots Nos 125, 111, 67 and 117 within the municipality of Cyclists and the execution of a photovoltaic installation with an installed capacity of 0.031 MW covering the company’s own needs on electricity. Piasecka 32 A, Ktowel in the Municipality of Mełgiev. The applicant is entitled to the property on which the project will be implemented. The plant will be composed of photovoltaic panels installed on steel wafers made from galvanised steel and aluminium with a slope of 36o, connected to inverters with a efficiency of at least 98 %, a n nn/SN station. On the other hand, the roof installation will consist of 2 kW (or grid) of 17.98 kW and the off-grid part B with an energy storage capacity and system to optimise the continuous labour efficiency of each module, thanks to a system that yields up to 25 % more energy from each module. These were presented in detail in the technical projects and the financial statements. Due to the location of both installations and the advanced technology, the planned installations will be able to produce around 672 MWh of electricity per year, including a photovoltaic farm of 640 MWh for sale, and 32 MWh will be used to provide the own needs of the company active in Kropcu. The electricity generated will be supplied to the energy network SN 15 kV via a transformer station n/SN. The lifetime of the farm is 25 years. The project will be implemented in 2018. at the date of the application, the applicant has all formal-legal documents, including the permission to build and secure the own contribution, there is no risk that the project will not be realised for reasons beyond the applicant’s control. The project will be carried out on the basis of indirect payment claims. As a result of the project, CO2 emissions will be reduced to the atmosphere by 223.29 t. (English) | |||
Property / summary: The project involves the construction of a PV power plant with an installed capacity of 0.6 MW and a SN cable line on plots Nos 125, 111, 67 and 117 within the municipality of Cyclists and the execution of a photovoltaic installation with an installed capacity of 0.031 MW covering the company’s own needs on electricity. Piasecka 32 A, Ktowel in the Municipality of Mełgiev. The applicant is entitled to the property on which the project will be implemented. The plant will be composed of photovoltaic panels installed on steel wafers made from galvanised steel and aluminium with a slope of 36o, connected to inverters with a efficiency of at least 98 %, a n nn/SN station. On the other hand, the roof installation will consist of 2 kW (or grid) of 17.98 kW and the off-grid part B with an energy storage capacity and system to optimise the continuous labour efficiency of each module, thanks to a system that yields up to 25 % more energy from each module. These were presented in detail in the technical projects and the financial statements. Due to the location of both installations and the advanced technology, the planned installations will be able to produce around 672 MWh of electricity per year, including a photovoltaic farm of 640 MWh for sale, and 32 MWh will be used to provide the own needs of the company active in Kropcu. The electricity generated will be supplied to the energy network SN 15 kV via a transformer station n/SN. The lifetime of the farm is 25 years. The project will be implemented in 2018. at the date of the application, the applicant has all formal-legal documents, including the permission to build and secure the own contribution, there is no risk that the project will not be realised for reasons beyond the applicant’s control. The project will be carried out on the basis of indirect payment claims. As a result of the project, CO2 emissions will be reduced to the atmosphere by 223.29 t. (English) / rank | |||
Normal rank |
Revision as of 09:27, 9 March 2020
Project in Poland financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | Construction of photovoltaic installations in the towns of Ludiins and Crete |
Project in Poland financed by DG Regio |
Statements
1,350,723.17 zloty
0 references
3,162,498.82 zloty
0 references
75.24 percent
0 references
1 March 2018
0 references
10 July 2019
0 references
SŁOMKA ROBERT "CEJSI-CAR" ROBERT SŁOMKA
0 references
Przedmiotem projektu jest budowa elektrowni fotowoltaicznej o mocy zainstalowanej 0,6 MW oraz linii kablowej SN na działkach nr 125, 111, 67 i 117 w obrębie Gminy Cyców oraz wykonanie instalacji fotowoltaicznej o mocy zainstalowanej 0,031 MW pokrywającej potrzeby własne przedsiębiorstwa na energie elektryczną, ul. Piasecka 32 A, Krępiec w Gmina Mełgiew. Wnioskodawca posiada prawa do nieruchomości, na których będzie realizowany projekt. Elektrownia będzie się składać z paneli fotowoltaicznych zainstalowanych na stelażach wykonanych z ocynkowanej stali i aluminium o kacie nachylenia 36o, podłączonych do inwerterów o sprawności co najmniej 98%, stacji nn/SN. Natomiast instalacja dachowa będzie się składać z 2 części A (on-grid) o mocy 17,98 kW oraz części B (off-grid) o mocy 12,18 kW wraz z magazynem energii oraz systemem optymalizacji monitorującym w trybie ciągłym wydajność pracy każdego modułu, dzięki systemowi można uzyskać wydajność do 25 % więcej energii z każdego modułu.. Szczegółowo powyższe przedstawiono w projektach technicznych oraz kosztorysach. Ze względu na położenie obydwu instalacji oraz zaawansowaną technologię projektowane instalacje będzie w stanie wyprodukować rocznie łącznie około 672 MWh energii elektr., w tym przez farmę fotowoltaiczną 640 MWh na sprzedaż, a 32 MWh będzie zużyte na zapewnienie potrzeb własnych przedsiębiorstwa prowadzącego działalność w Krępcu. Wytworzona energia elektr. będzie dostarczana do sieci energetycznej SN 15 kV poprzez stację transformatorową nn/SN. Czas eksploatacji farmy to 25 lat. Projekt będzie realizowany w 2018 r. Na dzień złożenia wniosku Wnioskodawca posiada wszystkie formalno-prawne dokumenty, włącznie z pozwoleniem na budowę i zabezpieczeniem wkładu własnego, nie występuje ryzyko nie zrealizowania projektu z przyczyn niezależnych od Wnioskodawcy. Projekt będzie realizowany na zasadzie pośrednich wniosków o płatność. W wyniku realizacji projektu nastąpi zmniejszenie emisji CO2 do atmosfery o 223,29 t. (Polish)
0 references
The project involves the construction of a PV power plant with an installed capacity of 0.6 MW and a SN cable line on plots Nos 125, 111, 67 and 117 within the municipality of Cyclists and the execution of a photovoltaic installation with an installed capacity of 0.031 MW covering the company’s own needs on electricity. Piasecka 32 A, Ktowel in the Municipality of Mełgiev. The applicant is entitled to the property on which the project will be implemented. The plant will be composed of photovoltaic panels installed on steel wafers made from galvanised steel and aluminium with a slope of 36o, connected to inverters with a efficiency of at least 98 %, a n nn/SN station. On the other hand, the roof installation will consist of 2 kW (or grid) of 17.98 kW and the off-grid part B with an energy storage capacity and system to optimise the continuous labour efficiency of each module, thanks to a system that yields up to 25 % more energy from each module. These were presented in detail in the technical projects and the financial statements. Due to the location of both installations and the advanced technology, the planned installations will be able to produce around 672 MWh of electricity per year, including a photovoltaic farm of 640 MWh for sale, and 32 MWh will be used to provide the own needs of the company active in Kropcu. The electricity generated will be supplied to the energy network SN 15 kV via a transformer station n/SN. The lifetime of the farm is 25 years. The project will be implemented in 2018. at the date of the application, the applicant has all formal-legal documents, including the permission to build and secure the own contribution, there is no risk that the project will not be realised for reasons beyond the applicant’s control. The project will be carried out on the basis of indirect payment claims. As a result of the project, CO2 emissions will be reduced to the atmosphere by 223.29 t. (English)
0 references
Identifiers
RPLU.04.02.00-06-0016/17