Construction of 110/15 kV Szczecin kV station to enable the development of renewable energy in western Poland (Q84424): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Changed an Item: Label in wikidata changed)
(‎Created claim: summary (P836): The main objective of this project is to increase the capacity of connecting new generating capacity from renewable energy sources to the electricity grid in the territory of the municipality of Poznań, in particular its south-eastern part, as well as to the municipalities of Kleszczevo and Kórnik.This will be achieved by building a new station of 110 KV Szczepankowo.It is planned to invest in one investment task., Adding English summary)
Property / summary
 
The main objective of this project is to increase the capacity of connecting new generating capacity from renewable energy sources to the electricity grid in the territory of the municipality of Poznań, in particular its south-eastern part, as well as to the municipalities of Kleszczevo and Kórnik.This will be achieved by building a new station of 110 KV Szczepankowo.It is planned to invest in one investment task. (English)
Property / summary: The main objective of this project is to increase the capacity of connecting new generating capacity from renewable energy sources to the electricity grid in the territory of the municipality of Poznań, in particular its south-eastern part, as well as to the municipalities of Kleszczevo and Kórnik.This will be achieved by building a new station of 110 KV Szczepankowo.It is planned to invest in one investment task. (English) / rank
 
Normal rank

Revision as of 09:39, 4 March 2020

Project in Poland financed by DG Regio
Language Label Description Also known as
English
Construction of 110/15 kV Szczecin kV station to enable the development of renewable energy in western Poland
Project in Poland financed by DG Regio

    Statements

    0 references
    10,658,085.26 zloty
    0 references
    2,557,940.4624 Euro
    13 January 2020
    0 references
    18,712,974.0 zloty
    0 references
    4,491,113.76 Euro
    13 January 2020
    0 references
    70.07 percent
    0 references
    4 May 2017
    0 references
    31 December 2020
    0 references
    ENEA OPERATOR SP. Z O.O.
    0 references
    Podstawowym celem przedmiotowego Projektu jest zwiększenie potencjału przyłączania nowych mocy wytwórczych z odnawialnych źródeł energii do sieci elektroenergetycznej na terenie gminy Poznań, a w szczególności jej południowo-wschodniej części, a także gmin Kleszczewo oraz Kórnik. Cel ten zostanie osiągnięty poprzez budowę nowej stacji 110 KV Szczepankowo. Planuje się realizację inwestycji w ramach jednego zadania inwestycyjnego. (Polish)
    0 references
    The main objective of this project is to increase the capacity of connecting new generating capacity from renewable energy sources to the electricity grid in the territory of the municipality of Poznań, in particular its south-eastern part, as well as to the municipalities of Kleszczevo and Kórnik.This will be achieved by building a new station of 110 KV Szczepankowo.It is planned to invest in one investment task. (English)
    0 references

    Identifiers

    POIS.01.01.02-00-0012/17
    0 references