I/11 road Nebors — Oldřichovice — Bystrice (2nd phase) _1 (Q72441): Difference between revisions
Jump to navigation
Jump to search
(Changed an Item: Label in wikidata changed) |
(Created claim: summary (P836): The purpose of the project is the construction of I/11 in category S 24,5/100, in category S 11,099, in the order of km (construction I/11 Neory — Oldřichovice 4.860 km and construction I/11 Oldrich — Bystrice 6.239 km), two lanes in each direction and an extra-level connection of roads. The newly built I/11 road in the Neory — Oldřichovice — Bystřice, is part of the definitive solution of the link between the D48 motorway and the Slovak Republi...) |
||
Property / summary | |||
The purpose of the project is the construction of I/11 in category S 24,5/100, in category S 11,099, in the order of km (construction I/11 Neory — Oldřichovice 4.860 km and construction I/11 Oldrich — Bystrice 6.239 km), two lanes in each direction and an extra-level connection of roads. The newly built I/11 road in the Neory — Oldřichovice — Bystřice, is part of the definitive solution of the link between the D48 motorway and the Slovak Republic and the GOI. The European transport corridor by road I/68 and I/11. (English) | |||
Property / summary: The purpose of the project is the construction of I/11 in category S 24,5/100, in category S 11,099, in the order of km (construction I/11 Neory — Oldřichovice 4.860 km and construction I/11 Oldrich — Bystrice 6.239 km), two lanes in each direction and an extra-level connection of roads. The newly built I/11 road in the Neory — Oldřichovice — Bystřice, is part of the definitive solution of the link between the D48 motorway and the Slovak Republic and the GOI. The European transport corridor by road I/68 and I/11. (English) / rank | |||
Normal rank |
Revision as of 19:57, 26 February 2020
Project in Czech Republic financed by DG Regio
Language | Label | Description | Also known as |
---|---|---|---|
English | I/11 road Nebors — Oldřichovice — Bystrice (2nd phase) _1 |
Project in Czech Republic financed by DG Regio |
Statements
1,825,092,046.05 Czech koruna
0 references
2,232,277,930.0 Czech koruna
0 references
81.759176199444 percent
0 references
1 January 2016
0 references
30 November 2019
0 references
Ředitelství silnic a dálnic ČR
0 references
14000
0 references
Předmětem projektu je výstavba přeložky silnice I/11 v kategorii S 24,5/100 v celk. délce hl. trasy 11,099 km (stavba I/11 Nebory - Oldřichovice 4,860 km a stavba I/11 Oldřichovice - Bystřice 6,239 km), o dvou jízdních pruzích v každém směru a mimoúrovňovým napojením křižujících komunikací. Nově budovaná silnice I/11 v úseku Nebory - Oldřichovice - Bystřice je součástí definitivního řešení propojení dálnice D48 se Slovenskou republikou a VI. Evropského dopravního koridoru po silnici I/68 a I/11. (Czech)
0 references
The purpose of the project is the construction of I/11 in category S 24,5/100, in category S 11,099, in the order of km (construction I/11 Neory — Oldřichovice 4.860 km and construction I/11 Oldrich — Bystrice 6.239 km), two lanes in each direction and an extra-level connection of roads. The newly built I/11 road in the Neory — Oldřichovice — Bystřice, is part of the definitive solution of the link between the D48 motorway and the Slovak Republic and the GOI. The European transport corridor by road I/68 and I/11. (English)
0 references
Identifiers
CZ.04.2.39/0.0/0.0/16_007/0000047