Modernisation of stations 110/SN Pakość, Jasiniec, Mogilno, Przechowo and Kruszwica to improve energy security (Q2693050): Difference between revisions
Jump to navigation
Jump to search
(Changed claim: EU contribution (P835): 6,561,802.73 euro) |
(Changed claim: budget (P474): 10,001,277.0 euro) |
||
Property / budget: 10,001,277.0 Euro / rank | Property / budget: 10,001,277.0 Euro / rank | ||
Preferred rank |
Revision as of 16:34, 21 September 2021
Project Q2693050 in Poland
Language | Label | Description | Also known as |
---|---|---|---|
English | Modernisation of stations 110/SN Pakość, Jasiniec, Mogilno, Przechowo and Kruszwica to improve energy security |
Project Q2693050 in Poland |
Statements
29,517,781.08 zloty
0 references
44,990,000.0 zloty
0 references
65.61 percent
0 references
1 July 2020
0 references
30 April 2023
0 references
ENEA OPERATOR SPÓŁKA Z OGRANICZONĄ ODPOWIEDZIALNOŚCIĄ
0 references
Projekt obejmuje przebudowę pięciu istniejących stacji elektroenergetycznych GPZ 110/15 kV: Pakość, Jasiniec, Mogilno, Przechowo i Kruszwica. Stacje te stanowić będą element sieci dystrybucyjnej na napięciu 110 kV, na której odbywa się transformacja energii elektrycznej na napięcie 15 kV. Projekt jest realizowany w trybie pod klucz. (Polish)
0 references
The project involves the reconstruction of five existing power stations GPZ 110/15 kV: Packet, Jasiniec, Mogilno, Containment and Kruszwica. These stations will be part of the 110 kV distribution network on which electricity is transformed to 15 kV. The project is carried out in turnkey mode. (English)
7 July 2021
0 references
Identifiers
POIS.07.01.00-00-0006/19
0 references