Reconstruction of the main state motorway A9 Riga (Skulte) – Liepaja, km 97.58-99.74 and 102.92-113.13 duvets (Q3057600): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Created claim: summary (P836): The aim of the project is to rebuild the duvet (increasing the bearing capacity of the duvet), which includes construction of new asphalt concrete pavement, reconstruction of culverts, which will ensure comfortable and safe driving conditions for road users. The total planned duration of the project is 27 months. The estimated total cost of the project is EUR 14394009,7. As a result of the project, the main state motorway A9 Riga (Skulte) will b...)
(‎Changed label, description and/or aliases in en: translated_label)
label / enlabel / en
 
Reconstruction of the main state motorway A9 Riga (Skulte) – Liepaja, km 97.58-99.74 and 102.92-113.13 duvets

Revision as of 12:47, 15 July 2021

Project Q3057600 in Latvia
Language Label Description Also known as
English
Reconstruction of the main state motorway A9 Riga (Skulte) – Liepaja, km 97.58-99.74 and 102.92-113.13 duvets
Project Q3057600 in Latvia

    Statements

    0 references
    0 references
    0 references
    10,273,001.89 Euro
    0 references
    12,085,884.58 Euro
    0 references
    12 May 2017
    0 references
    11 August 2019
    0 references
    Satiksmes ministrija
    0 references
    0 references
    0 references

    56°39'57.35"N, 22°29'37.03"E
    0 references

    56°39'51.98"N, 22°30'8.89"E
    0 references
    Projekta mērķis ir veikt segas pārbūvi (paaugstinot segas nestspēju), kas ietver jauna asfaltbetona seguma izbūvi, caurteku pārbūvi, kā rezultātā tiks nodrošināti autoceļu lietotājiem komfortabli un droši braukšanas apstākļi. Plānotais kopējais projekta īstenošanas ilgums 27 mēneši. Projekta plānotās kopējās izmaksas 14 394 009,7 euro. Projekta īstenošanas rezultātā tiks sakārtots valsts galvenā autoceļa A9 Rīga ( Skulte) - Liepāja, km 97,58 – 99,74 un 102,92 – 113,13 posms 12,37 km garumā. Projektā ietvertā autoceļa posma maksimālā autotransporta dzenošās ass slodze pēc projekta īstenošanas būs 11,5 tonnas un maksimālā nekontrolētā transportlīdzekļa pilnā masa būs 44 tonnas. (Latvian)
    0 references
    The aim of the project is to rebuild the duvet (increasing the bearing capacity of the duvet), which includes construction of new asphalt concrete pavement, reconstruction of culverts, which will ensure comfortable and safe driving conditions for road users. The total planned duration of the project is 27 months. The estimated total cost of the project is EUR 14394009,7. As a result of the project, the main state motorway A9 Riga (Skulte) will be arranged – Liepaja, km 97.58-99.74 and 102.92-113.13 section 12.37 km. The maximum driving axle load on the road section covered by the project will be 11.5 tonnes and the maximum uncontrolled vehicle mass will be 44 tonnes. (English)
    15 July 2021
    0 references
    Cieceres pag., Saldus nov.
    0 references
    Saldus nov.
    0 references
    Zirņu pag., Saldus nov.
    0 references

    Identifiers

    6.1.5.0/17/I/002
    0 references