Q2692770 (Q2692770): Difference between revisions
Jump to navigation
Jump to search
(Changed an Item: Edited by the materialized bot - inferring region from the coordinates) |
(Created claim: summary (P836): The objective of the project is to build an agricultural biogas plant with a capacity of 0.499 MWe and 0.54 MWc, producing electricity and heat in high-efficiency cogeneration technology. The subject matter of the project will be carried out under the following tasks: Activity 1. Construction of a biogas plant with a capacity of 0.499 MW (qualified): 1) Construction of primary fermentation tank (so-called fermenter) – 1 pcs. 2) Construction of s...) |
||||||||||||||
Property / summary | |||||||||||||||
The objective of the project is to build an agricultural biogas plant with a capacity of 0.499 MWe and 0.54 MWc, producing electricity and heat in high-efficiency cogeneration technology. The subject matter of the project will be carried out under the following tasks: Activity 1. Construction of a biogas plant with a capacity of 0.499 MW (qualified): 1) Construction of primary fermentation tank (so-called fermenter) – 1 pcs. 2) Construction of secondary fermentation tank (so-called dofermentor) – 1 pcs. 3) Construction of digestate storage tank in the form of lagoon – 1 pcs. 4) Buffer tank construction for liquid substrates (so-called pre-tank) – 1 pcs. 5) Construction of storage tank for liquid substrates – 1 pcs. 6) Construction of a crossing silo for storage of solid substrates – 1 pcs. 7) Construction of installation chess – 1 pcs. 8) Construction of gas condensation chess – pcs. 1 9) Construction of the control room building – 1 pcs. 10) Purchase and installation of transformer station 0.4/15 kV. 11) Purchase and installation of a cogeneration unit with a total power of 499 kW together with technical equipment – 1 pcs. 12) Purchase and installation of mobile container boiler room with power max. 500 kW – 1 pcs. 13) Purchase and assembly of a firefighter tank with a capacity of about 150 m³ Task 2. Construction of roads and squares (qualified) – paved areas of approximately 1480 m² will be built. Task 3. Construction supervision (qualified) – work carried out under Tasks 1 and 2. Task 4. Promotion of the project (ineligible). The installation complies with the definition of high-efficiency cogeneration set out in Annex II to Directive 2012/27/EU. The electricity capacity of the cogeneration unit is 0.499 MWe, hence the installation fulfils the definition of a small-scale cogeneration unit in accordance with Article 2, point. 38 of Directive 2012/27/EU. (English) | |||||||||||||||
Property / summary: The objective of the project is to build an agricultural biogas plant with a capacity of 0.499 MWe and 0.54 MWc, producing electricity and heat in high-efficiency cogeneration technology. The subject matter of the project will be carried out under the following tasks: Activity 1. Construction of a biogas plant with a capacity of 0.499 MW (qualified): 1) Construction of primary fermentation tank (so-called fermenter) – 1 pcs. 2) Construction of secondary fermentation tank (so-called dofermentor) – 1 pcs. 3) Construction of digestate storage tank in the form of lagoon – 1 pcs. 4) Buffer tank construction for liquid substrates (so-called pre-tank) – 1 pcs. 5) Construction of storage tank for liquid substrates – 1 pcs. 6) Construction of a crossing silo for storage of solid substrates – 1 pcs. 7) Construction of installation chess – 1 pcs. 8) Construction of gas condensation chess – pcs. 1 9) Construction of the control room building – 1 pcs. 10) Purchase and installation of transformer station 0.4/15 kV. 11) Purchase and installation of a cogeneration unit with a total power of 499 kW together with technical equipment – 1 pcs. 12) Purchase and installation of mobile container boiler room with power max. 500 kW – 1 pcs. 13) Purchase and assembly of a firefighter tank with a capacity of about 150 m³ Task 2. Construction of roads and squares (qualified) – paved areas of approximately 1480 m² will be built. Task 3. Construction supervision (qualified) – work carried out under Tasks 1 and 2. Task 4. Promotion of the project (ineligible). The installation complies with the definition of high-efficiency cogeneration set out in Annex II to Directive 2012/27/EU. The electricity capacity of the cogeneration unit is 0.499 MWe, hence the installation fulfils the definition of a small-scale cogeneration unit in accordance with Article 2, point. 38 of Directive 2012/27/EU. (English) / rank | |||||||||||||||
Normal rank | |||||||||||||||
Property / summary: The objective of the project is to build an agricultural biogas plant with a capacity of 0.499 MWe and 0.54 MWc, producing electricity and heat in high-efficiency cogeneration technology. The subject matter of the project will be carried out under the following tasks: Activity 1. Construction of a biogas plant with a capacity of 0.499 MW (qualified): 1) Construction of primary fermentation tank (so-called fermenter) – 1 pcs. 2) Construction of secondary fermentation tank (so-called dofermentor) – 1 pcs. 3) Construction of digestate storage tank in the form of lagoon – 1 pcs. 4) Buffer tank construction for liquid substrates (so-called pre-tank) – 1 pcs. 5) Construction of storage tank for liquid substrates – 1 pcs. 6) Construction of a crossing silo for storage of solid substrates – 1 pcs. 7) Construction of installation chess – 1 pcs. 8) Construction of gas condensation chess – pcs. 1 9) Construction of the control room building – 1 pcs. 10) Purchase and installation of transformer station 0.4/15 kV. 11) Purchase and installation of a cogeneration unit with a total power of 499 kW together with technical equipment – 1 pcs. 12) Purchase and installation of mobile container boiler room with power max. 500 kW – 1 pcs. 13) Purchase and assembly of a firefighter tank with a capacity of about 150 m³ Task 2. Construction of roads and squares (qualified) – paved areas of approximately 1480 m² will be built. Task 3. Construction supervision (qualified) – work carried out under Tasks 1 and 2. Task 4. Promotion of the project (ineligible). The installation complies with the definition of high-efficiency cogeneration set out in Annex II to Directive 2012/27/EU. The electricity capacity of the cogeneration unit is 0.499 MWe, hence the installation fulfils the definition of a small-scale cogeneration unit in accordance with Article 2, point. 38 of Directive 2012/27/EU. (English) / qualifier | |||||||||||||||
point in time: 7 July 2021
|
Revision as of 13:23, 7 July 2021
Project Q2692770 in Poland
Language | Label | Description | Also known as |
---|---|---|---|
English | No label defined |
Project Q2692770 in Poland |
Statements
7,363,069.0 zloty
0 references
10,746,300.0 zloty
0 references
68.52 percent
0 references
1 January 2020
0 references
31 December 2021
0 references
FERMY TRZODY "POL-FERM" SPÓŁKA Z OGRANICZONĄ ODPOWIEDZIALNOŚCIĄ
0 references
Cel projektu Celem projektu jest budowa biogazowni rolniczej o mocy 0,499 MWe i 0,54 MWc, wytwarzającej energię elektryczną i cieplną w technologii wysokosprawnej kogeneracji. Zakres przedmiotowy projektu Przedmiotowy projekt realizowany będzie w ramach poniższych zadań: Zadanie 1. Budowa biogazowni o mocy 0,499 MW (kwalifikowane): 1) Budowa zbiornika fermentacji pierwotnej (tzw. fermentor) - 1 szt. 2) Budowa zbiornika fermentacji wtórnej (tzw. dofermentor) - 1 szt. 3) Budowa zbiornika do magazynowania pofermentu w postaci laguny - 1 szt. 4) Budowa zbiornika buforowego na substraty płynne (tzw. zbiornik wstępny) - 1 szt. 5) Budowa zbiornika magazynowego na substraty płynne – 1 szt. 6) Budowa przejazdowego silosu do magazynowania substratów stałych – 1 szt. 7) Budowa szachtu instalacyjnego – 1 szt. 8) Budowa szachtu kondensacji gazu – szt. 1 9) Budowa budynku sterowni –1 szt. 10) Zakup i instalacja stacji transformatorowej 0,4/15 kV. 11) Zakup i instalacja zespołu kogeneracyjnego o łącznej mocy 499 kW wraz z osprzętem technicznym – 1 szt. 12) Zakup i instalacja mobilnej kontenerowej kotłowni o mocy max. 500 kW – 1 szt. 13) Zakup i montaż zbiornika ppoż. o pojemności około 150 m3 Zadanie 2. Budowa dróg i placów (kwalifikowane) - wybudowane zostaną powierzchnie utwardzone o powierzchni około 1 480 m2. Zadanie 3. Nadzór budowlany (kwalifikowany) - nad pracami realizowanymi w ramach zadania 1 i 2. Zadanie 4. Promocja projektu (niekwalifikowany). Instalacja spełnia warunki definicji wysokosprawnej kogeneracji określone w załączniku II do Dyrektywy 2012/27/UE. Moc elektryczna jednostki kogeneracyjnej to 0,499 MWe, stąd też instalacja spełnia przesłanki definicji małoskalowej jednostki kogeneracyjnej, zgodnie z Art. 2, pkt. 38 dyrektywy 2012/27/UE. (Polish)
0 references
The objective of the project is to build an agricultural biogas plant with a capacity of 0.499 MWe and 0.54 MWc, producing electricity and heat in high-efficiency cogeneration technology. The subject matter of the project will be carried out under the following tasks: Activity 1. Construction of a biogas plant with a capacity of 0.499 MW (qualified): 1) Construction of primary fermentation tank (so-called fermenter) – 1 pcs. 2) Construction of secondary fermentation tank (so-called dofermentor) – 1 pcs. 3) Construction of digestate storage tank in the form of lagoon – 1 pcs. 4) Buffer tank construction for liquid substrates (so-called pre-tank) – 1 pcs. 5) Construction of storage tank for liquid substrates – 1 pcs. 6) Construction of a crossing silo for storage of solid substrates – 1 pcs. 7) Construction of installation chess – 1 pcs. 8) Construction of gas condensation chess – pcs. 1 9) Construction of the control room building – 1 pcs. 10) Purchase and installation of transformer station 0.4/15 kV. 11) Purchase and installation of a cogeneration unit with a total power of 499 kW together with technical equipment – 1 pcs. 12) Purchase and installation of mobile container boiler room with power max. 500 kW – 1 pcs. 13) Purchase and assembly of a firefighter tank with a capacity of about 150 m³ Task 2. Construction of roads and squares (qualified) – paved areas of approximately 1480 m² will be built. Task 3. Construction supervision (qualified) – work carried out under Tasks 1 and 2. Task 4. Promotion of the project (ineligible). The installation complies with the definition of high-efficiency cogeneration set out in Annex II to Directive 2012/27/EU. The electricity capacity of the cogeneration unit is 0.499 MWe, hence the installation fulfils the definition of a small-scale cogeneration unit in accordance with Article 2, point. 38 of Directive 2012/27/EU. (English)
7 July 2021
0 references
Identifiers
POIS.01.06.01-00-0028/19
0 references