Q2692727 (Q2692727): Difference between revisions

From EU Knowledge Graph
Jump to navigation Jump to search
(‎Changed an Item: Edited by the materialized bot - inferring region from the coordinates)
(‎Created claim: summary (P836): The adopted project implementation concept involves the construction of a smart electricity grid in the city under the rights of the district of Zielona Góra, the district of Nowosolski, the municipality of Nowa Sól and Kożuchów through the modernisation and reconstruction of the network, the automation of lines and stations as a result of the application of remote control and electrical security automation, including short-circuit current indic...)
Property / summary
 
The adopted project implementation concept involves the construction of a smart electricity grid in the city under the rights of the district of Zielona Góra, the district of Nowosolski, the municipality of Nowa Sól and Kożuchów through the modernisation and reconstruction of the network, the automation of lines and stations as a result of the application of remote control and electrical security automation, including short-circuit current indicators. The project provides for the automation of the network in the area of Distribution Districts Zielona Góra and Nowa Sól. The aim of the project is to ensure an efficient and technically and economically sustainable energy system with low losses and a high level of quality and security of supply and security. (English)
Property / summary: The adopted project implementation concept involves the construction of a smart electricity grid in the city under the rights of the district of Zielona Góra, the district of Nowosolski, the municipality of Nowa Sól and Kożuchów through the modernisation and reconstruction of the network, the automation of lines and stations as a result of the application of remote control and electrical security automation, including short-circuit current indicators. The project provides for the automation of the network in the area of Distribution Districts Zielona Góra and Nowa Sól. The aim of the project is to ensure an efficient and technically and economically sustainable energy system with low losses and a high level of quality and security of supply and security. (English) / rank
 
Normal rank
Property / summary: The adopted project implementation concept involves the construction of a smart electricity grid in the city under the rights of the district of Zielona Góra, the district of Nowosolski, the municipality of Nowa Sól and Kożuchów through the modernisation and reconstruction of the network, the automation of lines and stations as a result of the application of remote control and electrical security automation, including short-circuit current indicators. The project provides for the automation of the network in the area of Distribution Districts Zielona Góra and Nowa Sól. The aim of the project is to ensure an efficient and technically and economically sustainable energy system with low losses and a high level of quality and security of supply and security. (English) / qualifier
 
point in time: 7 July 2021
Timestamp+2021-07-07T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 13:22, 7 July 2021

Project Q2692727 in Poland
Language Label Description Also known as
English
No label defined
Project Q2692727 in Poland

    Statements

    0 references
    13,621,602.67 zloty
    0 references
    3,028,082.27 Euro
    0.2223 Euro
    0 references
    19,580,000.0 zloty
    0 references
    4,352,634.0 Euro
    0.2223 Euro
    0 references
    69.57 percent
    0 references
    1 September 2019
    0 references
    31 December 2022
    0 references
    ENEA OPERATOR SP. Z O.O.
    0 references
    0 references

    52°6'0.7"N, 15°21'37.8"E
    0 references
    Przyjęta koncepcja realizacji projektu zakłada budowę elektroenergetycznej sieci inteligentnej na terenie miasta na prawach powiatu Zielona Góra, powiatu nowosolskiego, gminy Nowa Sól i Kożuchów poprzez modernizację i przebudowę sieci, automatyzację linii i stacji w wyniku zastosowania zdalnego sterowania i elektroenergetycznej automatyki zabezpieczeniowej, w tym wskaźników prądów zwarciowych. W projekcie przewidziano automatyzację sieci na obszarze Rejonów Dystrybucji Zielona Góra oraz Nowa Sól. Celem projektu jest zapewnienie efektywnego i zrównoważonego pod względem ekonomicznym i technicznym systemu energetycznego, o niskim poziomie strat oraz wysokim poziomie jakości oraz bezpieczeństwa dostaw i ochrony. (Polish)
    0 references
    The adopted project implementation concept involves the construction of a smart electricity grid in the city under the rights of the district of Zielona Góra, the district of Nowosolski, the municipality of Nowa Sól and Kożuchów through the modernisation and reconstruction of the network, the automation of lines and stations as a result of the application of remote control and electrical security automation, including short-circuit current indicators. The project provides for the automation of the network in the area of Distribution Districts Zielona Góra and Nowa Sól. The aim of the project is to ensure an efficient and technically and economically sustainable energy system with low losses and a high level of quality and security of supply and security. (English)
    7 July 2021
    0 references

    Identifiers

    POIS.01.04.01-00-0005/19
    0 references