(‎Created claim: summary (P836): The subject of the feasibility study is the construction of an installation for the production of heat from biomass with a capacity of 5.1 MW in Tomaszów Mazowiecki. The project will be implemented on the basis of typical technical solutions available on the market. This will allow to maintain the durability of the project through access to spare parts and authorised service, as well as to use the competitive procedure in the purchase of the dev...)
Property / summary
 
The subject of the feasibility study is the construction of an installation for the production of heat from biomass with a capacity of 5.1 MW in Tomaszów Mazowiecki. The project will be implemented on the basis of typical technical solutions available on the market. This will allow to maintain the durability of the project through access to spare parts and authorised service, as well as to use the competitive procedure in the purchase of the device together with the installation without the need to draw up technical documentation of the device. The implementation of the project will result in a reduction in emissions from a conventional heating plant supplying network heat to date. (English)
Property / summary: The subject of the feasibility study is the construction of an installation for the production of heat from biomass with a capacity of 5.1 MW in Tomaszów Mazowiecki. The project will be implemented on the basis of typical technical solutions available on the market. This will allow to maintain the durability of the project through access to spare parts and authorised service, as well as to use the competitive procedure in the purchase of the device together with the installation without the need to draw up technical documentation of the device. The implementation of the project will result in a reduction in emissions from a conventional heating plant supplying network heat to date. (English) / rank
 
Normal rank
Property / summary: The subject of the feasibility study is the construction of an installation for the production of heat from biomass with a capacity of 5.1 MW in Tomaszów Mazowiecki. The project will be implemented on the basis of typical technical solutions available on the market. This will allow to maintain the durability of the project through access to spare parts and authorised service, as well as to use the competitive procedure in the purchase of the device together with the installation without the need to draw up technical documentation of the device. The implementation of the project will result in a reduction in emissions from a conventional heating plant supplying network heat to date. (English) / qualifier
 
point in time: 7 July 2021
Timestamp+2021-07-07T00:00:00Z
Timezone+00:00
CalendarGregorian
Precision1 day
Before0
After0

Revision as of 13:21, 7 July 2021

Project Q2692716 in Poland
Language Label Description Also known as
English
No label defined
Project Q2692716 in Poland

    Statements

    0 references
    4,660,000.0 zloty
    0 references
    1,035,918.0 Euro
    0.2223 Euro
    0 references
    10,000,000.0 zloty
    0 references
    2,223,000.0 Euro
    0.2223 Euro
    0 references
    46.6 percent
    0 references
    30 November 2020
    0 references
    31 December 2022
    0 references
    ZAKŁAD USŁUG TECHNICZNYCH SP. Z O.O.
    0 references
    0 references

    51°31'10.2"N, 20°2'1.7"E
    0 references
    Przedmiotem studium wykonalności jest Budowa instalacji produkcji ciepła z biomasy o mocy 5,1 MW w Tomaszowie Mazowieckim. Projekt zostanie zrealizowany w oparciu o typowe, dostępne na rynku rozwiązania techniczne. Pozwoli to na utrzymanie trwałości projektu poprzez dostęp do części zamiennych i autoryzowanego serwisu, a także pozwoli na zastosowanie procedury konkurencyjnej w zakupie urządzenia wraz z instalacją bez konieczności sporządzania dokumentacji technicznej urządzenia. Wskutek realizacji przedsięwzięcia nastąpi ograniczenie emisji z instalacji ciepłowni konwencjonalnej dostarczającej dotychczas ciepło sieciowe. (Polish)
    0 references
    The subject of the feasibility study is the construction of an installation for the production of heat from biomass with a capacity of 5.1 MW in Tomaszów Mazowiecki. The project will be implemented on the basis of typical technical solutions available on the market. This will allow to maintain the durability of the project through access to spare parts and authorised service, as well as to use the competitive procedure in the purchase of the device together with the installation without the need to draw up technical documentation of the device. The implementation of the project will result in a reduction in emissions from a conventional heating plant supplying network heat to date. (English)
    7 July 2021
    0 references

    Identifiers

    POIS.01.01.01-00-0021/19
    0 references